Ref#:21A
Forward pass
o Backward pass
Total float = late finish – early finish
2. Normal Distribution
1σ = 68.27%
2σ = 95.45%
3σ = 99.73%
EAC = AC + (BAC – EV) ÷ (CPI)(SPI)
FORMULAS, EQUATIONS,
AND RULES
1. Project Network Schedules
Network schedules are created after
duration estimates and the relationships between
the work packages
have been determined. Following
a path(s) from left to right makes a forward pass.
o Yields early start
(ES) and early finish (EF)
dates
o Early finish = early start + duration
o RULE: If there are multiple predecessors, use LATEST
EF to
determine successor
ES
After all paths have been given
their forward path,
they are traversed from
right to left to make a backward pass.
Yields late start (LS) and late finish (LF) dates
Late start = late finish – duration
RULE: If there are multiple successors, use EARLIEST LS to
determine predecessor LF
Once the forward and backward passes have been completed, the total float for
the
node can be calculated by:
The normal distribution,
commonly known as the bell curve,
is
a symmetrical distribution, as shown inFigure 1-1. Each normal curve
can be distinctly described using the mean and sum of the values. The
possibility of achieving the project objective
in the mean time or cost is 0%,
with
a 50% chance of falling below the mean
and a 50%
chance of exceeding
the
mean. Adding
one
or more standard deviations (σ)
to the mean increases the chances of falling
within
the range. The probability of falling within 1σ,
2σ, or 3σ from the mean is:
2σ = 95.45%
3σ = 99.73%
The beta distribution is like the triangular distribution except more weight is given
to the most likely estimate. This may result in either
a symmetrical or
an
asymmetrical (skewed
right or skewed left) graph. An asymmetrical graph is shown
in
Figure 1-3.
Where O = optimistic estimate,
ML = most likely estimate, and P = pessimistic estimate, variance for a task
(V)
is:
V = σ2
Mean (μ)
(μ) = (O + 4ML + P) ÷ 6
Standard deviation (σ)
σ = (P – O) ÷ 6
5. Statistical Sums
o The project mean is the sum
of the means of the individual tasks: μp = μ1 + μ2 + . . . + μn
o The project variance is the sum
of the variances of the individual tasks: Vp = V1 + V2 + . . . + Vn
o The project standard deviation
is
the square root of the project variance:
6. Earned Value Management
Earned value management is used to
monitor the progress of a project and is an
analytical technique. It uses three independent variables:
Planned value (PV): the budget or the portion of
the approved cost estimate planned to be spent during
a given period
Actual cost (AC): the total of direct and indirect costs incurred in accomplishing work
during a given
period
Earned value (EV): the budget for
the
work accomplished in a given
period
These three values are used in combination to provide measures of whether
or not work is proceeding
as planned. They combine to
yield the following important formulas:
Cost variance (CV) = EV – AC
Schedule variance (SV) = EV – PV
Cost performance index (CPI) = EV ÷ AC
Schedule performance index (SPI) = EV ÷ PV
Negative
CV indicates cost overrun. Negative
SV indicates a project is behind schedule.
A CPI greater
than
1.0
indicates costs are below budget.
An SPI greater than 1.0 indicates a project is ahead of schedule.
A CPI less than
1.0
indicates costs are over budget. An
SPI less than 1.0 indicates a project is behind
schedule.
7. Estimate at
Completion
An estimate
at completion (EAC) is the amount we
expect the total project to cost on completion
and as of the “data date”
(time now).
There are four methods listed in the PMBOK® Guide for computing EAC. Three of these methods use a formula to
calculate EAC. Each of these starts with AC, or
actual costs
to date,
and
uses a different technique to estimate the work remaining
to be completed,
or ETC.
The question of which to use depends on
the individual situation
and
the credibility of the actual work
performed compared to the budget up
to that point.
A new estimate
is most applicable when the
actual performance to
date shows that the
original estimates were fundamentally flawed or when
they are no longer
accurate because of
changes in conditions relating to
the
project:
EAC = AC + New
Estimate for Remaining Work
The original estimate formula is most applicable when actual variances to date are seen as
being the exception,
and the expectations for
the
future are that the original estimates are
more reliable than the actual work effort efficiency to
date:
EAC = AC + (BAC – EV)
The performance estimate low formula is most applicable when future variances are
projected to
approximate the same level as current variances:
AC = AC + (BAC – EV) ÷ CPI
A shortcut version of
this formula is:
EAC = BAC ÷ CPI
The performance estimate high formula is used when
the
project is over
budget
and
the schedule impacts the work remaining
to be completed:
EAC = AC + (BAC – EV) ÷ (CPI)(SPI)
SPI
= EV ÷ PV
8. Remaining
Budget
RB = Remaining PV
or
RB = BAC – EV
9. Budget at Completion
BAC = the total budgeted cost of all approved activities
10. Estimate
to Complete
The estimate to
complete (ETC) is the estimate for
completing the remaining work
for a scheduled activity. Like the EAC formulas above, there are three variations:
o ETC = an entirely new estimate
o ETC = (BAC – EV) when
past variances are considered to be atypical
o ETC = (BAC – EV) ÷ CPI when
prior variances are considered to be typical of future variances
11. Communications Channels
o Channels = [n(n – 1)] ÷ 2
where “n” = the number of people
12. Rule of Seven
In a control chart, the “rule of seven” is a heuristic stating that if seven or more observations
occur
in one direction either upward or
downward, or a run
of seven
observations occurs either above or below the
mean, even though
they may be within
the control lines, they should be investigated to
determine if they
have an assignable cause.
The reason for this rule is that, if the process is operating normally, the
observations will follow a random pattern; it is extremely unlikely that seven observations in a row
would occur in
the same direction
above or below the mean.
The probability of any given point going up
or down or being above or below the mean
is
50-50 (i.e.,
50%). The probability of seven
observations being
consecutively in one direction
or above or below the mean
would be calculated as 0.507, which equals 0.0078 (i.e.,
much less than
1%).
No comments:
Post a Comment